MAE provided geotechnical explorations and analysis for design of the initial phase of this project including below-grade pipelines, site access roadways, parking areas, and stormwater management ponds. Field work included performing 47 pond and roadway auger borings, 7 Standard Penetration Test (SPT) borings for pipelines, and pond permeability testing. Analysis included groundwater drawdown (baseflow) to determine if pond construction would impact near-by wetlands. Recommendations were provided for construction of structures, pavement and ponds.